I m having trouble locating good wall to roof flashing detail for hardie siding.
Exterior siding belly band flashing detail.
This is sometimes referred to as a belly band.
Leave a 1 4 minimum gap between cladding termination and sloped metal drip flashings shown in figure 1 1 c this detail can also apply to other flashing details such as.
Belly bands exterior penetrations etc.
I would slide it under the nail flange at the bottom of the window and it would end on the top of the nail flange on the siding where the water would drain into the bottom of the piece siding that when on next.
The flashing i used is a flat piece of metal.
Where the step flashing terminates along a sidewall is a common trouble spot for moisture problems.
If the shingle already has flashing on it the kickout flashing has to slip beneath it and you ll have to loosen or remove siding to do this.
Have water damage at the belly band.
In areas where snow may build up add a wide band of peel and stick membrane over the step flashing but under the sheathing wrap as shown.
One piece of siding installed vertically create a belly band trim joint with a piece of 1 x4 1 x6 or 1 x8 trim depending on preference and z flashing above and below fig.
It s very common in sacramento one of the most common areas of exterior water damage to wood trim occurs when a horizontal piece of wood is nailed to a wood surface on many two story buildings in sacramento there is a horizontal board that divides the upper and lower story.
One of the most vulnerable areas for siding is transitions.
J flashing on transitions.
Building siding flashing finish details for building corners use overlapping 1x4s or 1x6s at outside corners or use 5 4 stock for a heavier look.
The best solution is a preformed or custom bent kick out flashing to divert the water away from the siding.
Use a felt paper spline wrapped around the corner and extending 6 inches beyond the corner board to protect the joints where the siding meets the corner boards see figure 1 5 at left.
The roof will need to be reshingled in a couple years so i was thinking of doing a water table detail with a band board so that the band board could be popped off later if the counter flashing needs to be replaced or just taken off to get at the top shingles.